Efficient Evaluation Method of Operation Cost for Wastewater Treatment Plant by BTL Contract Type |
Keywords |
BTL (Build Transfer Lease);wastewater treatment plant;operation cost;regression analysis;임대형 민간투자사업;하수처리시설;운영비;회귀분석 |
Abstract |
The BTL (Build-Transfer-Lease) contract of construction project serves as a part for early establishment of industrial foundation for social overhead capital. However, project cost of BTL contract is focused on initial construction cost. Accordingly, operation cost is lowly evaluated because there is no standard criterion for estimating maintenance cost for the facility. The low operation cost can be a factor that reduces service quality of facility operation. This study suggests a resonable method for estimating cost and manpower in the operation phase by using the existing practical data for wastewater treatment plant by BTL contract. The results of the study can be used for evaluating rough operation cost and manpower of similar plant project by facility size. |