Title |
A Study on Efficiency Improvement through Productivity Analysis Based on TBM Operation Data |
Keywords |
a waterway tunnel works;lose time;boring length;boring length of rise forecast;수로터널현장;시간손실;굴진장;상승굴진장 |
Abstract |
This study presented the operation method through of productivity on eight analysis work items (TBM boring, cutter check and exchange, TBM maintenance, succeeding facilities, reinforcement in tunnel, operation alternation, a tram car) which have developed equipment at WRITH with TBM a waterway tunnel works. It was inquired lose time with analyzed result by work items and removed lose time. It was analyzed TBM boring length, TBM boring length percentage and TBM boring length time. This study analyzed TBM operation utility factor of a foreign work with TBM operation boring length percentage, a monthly average boring length, pure boring length percentage etc. and assumed a monthly average boring length and a monthly average boring length of rise forecast. Based on analyzed Data, TBM boring has been forecasted propriety pure boring length at compressive strength 675~1,662 ㎏f/㎠ |