Title Application Method of Phase Division of Fast Track for Construction Project with Complex Structures
Authors 김현수(Kim, Hyun Soo) ; 황재영(Hwang, Jae Yoeng) ; 강효정(Kang, Hyo Jeong) ; 박상미(Park, Sang Mi) ; 이재희(Lee, Jae Hee) ; 강인석(Kang, Leen Seok)
DOI https://doi.org/10.12652/Ksce.2022.42.1.0095
Page pp.95-105
ISSN 10156348
Keywords 패스트트랙; 표준공정; 공정분류체계; 축구전용경기장 Fast track; Standard schedule; Work breakdown structure; Football stadium
Abstract Recently, as the scale of a construction project has become larger and more complicated, there are many cases where construction projects with complex structures are carried out in a fast track method to save construction duration. In the fast track method, the proper division of construction phases is an important issue in determining the overall project period. This study presents a rational phase division method that can be applied when a construction project with complex structures is carried out as a fast track. For this study, a subdivided work breakdown structure (WBS) is developed using the construction of 4 soccer stadiums as application examples, and the schedule is analyzed by dividing the construction process of major phases. To this end, five proposals are applied to analyze the adequacy of the fast track phase division. For the draft with the minimum construction period, the fast track phase division and the schedule model of by each phase were presented. This methodology can have an application in the appropriate phase division and
schedule model by construction phase when fast track is applied in large construction project of a similar size.