Title Deriving Key Risk Sub-Clauses of FIDIC Conditions of Standard Subcontract -Based on FIDIC Conditions of Subcontract for Construction, edition 2011-
Authors 홍성열(Hong, Seong Yeoll) ; 제재용(Jei, Jae Yong) ; 서성철(Seo, Sung Chul) ; 박형근(Park, Hyung Keun)
DOI https://doi.org/10.12652/Ksce.2022.42.3.0439
Page pp.439-448
ISSN 10156348
Keywords 중소하도급업체; 하도급건설계약조건; 핵심 리스크 세부조항; 델파이기법; 국제컨설팅엔지니어연맹; 발생도와 영향도 리스크 매트릭스 Small and medium-sized subcontractor; Conditions of subcontract for construction; Key risk sub-clauses; Delphi technique; FIDIC; PI risk matrix
Abstract Recently, domestic small and medium-sized subcontractors participating in the overseas construction market are suffering from the continuous loss and damage due to the insufficient recognition of the importance of risk Sub-Clauses among conditions of subcontracts. Therefore, the need to derive risk Sub-Clauses for conditions of the subcontract has been raised, but until now, previous studies havebeen conducted focusing on deriving risk Sub-Clauses for standard conditions of contract for construction between the Employer and the Contractor. In this study, 52 risk Sub-Clauses were derived on the basis of the influence size of the Sub-Clauses through the Delphitechnique targeting 94 Sub-Clauses of conditions of standard subcontract for construction edition 2011, issued by the International Federation of Consulting Engineers (FIDIC) and In addition, 33 key risk Sub-Clauses were finally derived through the PI Risk Matrixby Probability and Impact. The results of this study provide will useful information on key risk Sub-Clauses that need to be reviewed in advance to minimize contractual risks at the stage of bidding and signing contracts for overseas subcontract construction projects.