Title |
Improvement Plan of Post Construction Evaluation: Focus on Construction Performance |
Authors |
박희성(Park, Heesung) ; 김태영(Kim, Tae Yeong) |
DOI |
https://doi.org/10.12652/Ksce.2024.44.3.0375 |
Keywords |
사후평가;성과;공사비;공사 기간;설계변경;건설 Post evaluation;Performance;Cost;Schedule;Change;Construction |
Abstract |
The size of the construction industry is increasing, and its impact on the entire national industry is also significant. However, construction cost increases, construction period delays, safety accidents, and quality problems occur during the construction process. This paper analyzed the construction cost, construction period, and change order performance for civil infrastructures for which post evaluation was performed. The analysis was conducted by dividing civil engineering facilities by type, construction nature, construction cost, contract nature, and delivery method. Planned and actual construction cost and period were compared during the planning, design, and construction process of civil engineering facilities. There is a possibility of input errors in project performance data, this paper proposes to the post-evaluation center should perform post-evaluation. Also, post-evaluation implementation guidelines for change orders should be revised. Additionally, further analysis of each facility was proposed through continuous data collection. |