Structural Restoration for the Electric Power Transmission Tower Damaged by Foundation Settlements
|
Authors |
이호범 ; 박종권 ; 김일수 ; 장일영 ; 송재호 |
Keywords |
송전철탑 ; 기초침하 ; 구조안전점검 ; 잭킹시스템 ; 부재보강 및 교체 Electric power transmission tower ; Structural safety inspection ; Jacking system ; Strengthening existing member |
Abstract |
Generally the capacities of electric power transmission tower's members are improved by increasing their stiffness nature through injection of grout or attachment of other structural stiffeners. Those are for upgrading their axial strength by fulfillment of proper materials into pipe members, increment of member dimension by addition of section, or a combination of the two. However the use of innovative and unusual procedures would be positively recommended for getting more stable state. It is that buckled members are replaced with lengthened and strengthened members. In providing the structural restoration procedures for the existing electric power transform tower whose main members have been damaged due to unequal foundation settlement, structural damage inspection works and numerical analyses for the damaged one and the restored one were done in detail at first. secondarily member-exchanging works using a newly-generated jacking system and strengthened members were achieved. This figures are to point clearly to inherent advantages attending the management of the towers.
|