Title |
A Study on the Mitigation of Construction Dispute in Public Projects |
Authors |
Cho Young-Jun ; Lee Sang-Beom |
Keywords |
Design Review ; Construction Dispute ; Mediation ; Arbitration ; Claim |
Abstract |
In Korea when change order was occurred, contract amount may be adjusted according to Government Contract Act. If the requirement of privy is fully accepted, conflict can't arise. Because of a misunderstanding and misappropriation of contract, a difference between the contract condition and job site, an errors & omissions of the design document, the contract disputes has been increased since the Seoul 2nd Metro Project claims alleged by 6 Contractors at Feb. 1998. To mitigate construction dispute, the preparation of through feasibility study, through design review and introduction of Professional Liability Insurance for Designer, and introduction of coercive arbitration clause in public construction, participation of construction engineer in arbitration process were suggested in this paper. |