Title Structure and Construction Technology Analysis about Construction Sequence Change for Superstructure Construction Period Reduction in Top-down Method
Authors Park, Yong-Hyeon ; Ju, Young-Kyu
DOI https://doi.org/10.5659/JAIK_SC.2019.35.6.101
Page pp.101-109
ISSN 1226-9107
Keywords Top down method ; Construction Sequence ; Construction Period Reduction ; Removable Deck Plate ; Core Wall Construction
Abstract The purpose of this study is to improve a general Top-Down construction process for superstructure construction period reduction. In a general Top-Down construction sequence, the ground floor slab is set up first. Subsequently, 1st basement level construction including core walls is constructed. Initiation of the ground level superstructure gets waited until then. In this study, removable deck plate installation on the bottom of the core walls of ground level is preceding the concrete casting, therefore, ground level superstructure construction is able to get started earlier. Up to first typical floor concrete casting, total of seventy-two working(calendar) days will be resulted in a reduction from the total construction periods.