Title |
CSFs Extraction and AHP Importance Analysis for Construction Technology Services Evaluation in terms of Construction Manager |
Authors |
Yang, Jin-Kook ; Hong, Seong-Wook |
DOI |
https://doi.org/10.5659/JAIK_SC.2020.36.3.129 |
Keywords |
Construction Manager(CMr); Construction Management Evaluation; Critical Success Factor; In-depth Interview; AHP Technique |
Abstract |
The current evaluation time period for the construction management service is the project completion or after project completion. Therefore,
the construction manager has the following problems. First, it is difficult to prepare the evaluation due to the new field movement of the
existing participating engineer. Next, the CM work is complex as well as extensive. Therefore, the critical success factors of the construction
technology services evaluation are required as a systematic performance standard of CM work. In this study, we extracted the critical success
factors that can systematically prepare the evaluation from the early stage of the project through in - depth interviews with experts. And, this
study was analyze the priority of each factor by using AHP technique. As a result, the most important factors were related to the
systemization of the preparation process, the construction manager work capabilities and practical construction management. And the priorities
of all factors were analyzed high in the factors suggested by the owner groups. The results of this analysis are expected to provide the
standards that construction management service performer carry out structured management of construction management throughout the project. |