Title |
Estimation of Optimum Construction Duration for Landscape Construction in Apartment Housing Project |
Authors |
윤은주(Yoon, Eun-Ju) ; 김미현(Kim, Mi-Hyeon) ; 윤석헌(Yun, Seok-Heon) |
DOI |
https://doi.org/10.5659/JAIK.2021.37.2.205 |
Keywords |
Landscape Construction; Construction Period; WBS(Work Breakdown Structure); Working day; Non-working day |
Abstract |
In a public construction project, the construction period is a factor that directly affects the safety of workers and the quality of the
construction, and securing the proper construction period and complying with the period is closely related to the success of the construction
work. Recently, the number of non-working day at domestic construction sites has been increasing due to institutional changes and climate
change. Accordingly, the importance of securing a proper construction period is emphasized. Previously, studies have been conducted on the
proper construction period, but most of them have been conducted on the construction work, and the research on landscaping work is
insufficient. However, in the case of landscape construction, most of the work is done externally, so it is often not carried out due to the
preceding work type and climate. Accordingly, it is important to secure a proper construction period for landscaping work and proceed with
the construction. For this purpose, the actual number of working days and the appropriate number of working days of landscaping works
constructed in domestic were investigated. According to the analysis, the number of proper construction period was the same or higher than
the actual number of working days in all works except for the packing closing work of more than 300 households. This means that the
current landscaping construction period is not sufficient, and it is deemed necessary to calculate the appropriate construction period by
deriving the factors influencing the work type. |