Title |
Development of Design Change VM Job Plan for Construction Work |
Authors |
남경우(Nam, Keong-Woo) ; 김종협(Kim, Jonghyeob) ; 장명훈(Jang, Myunghoun) |
DOI |
https://doi.org/10.5659/JAIK.2023.39.8.245 |
Keywords |
Design Change; Value Methodology; Value Engineering; Job Plan |
Abstract |
The standard VM Job Plan stipulates that a VM study target to be intensively invested in time and effort is selected. In case of design
change, the target is specified in advance, and the VM study team is already fully familiar with the relevant information. In addition, design
changes need to be carried out quickly and intensively in a short time at the site during construction. Therefore, in this study, separate from
the standardized process, in order to enable the client to effectively and smoothly conduct the VM Study, which is obligatory for design
changes accompanied by a 10% or more cost adjustment in the construction stage of construction works worth 10 billion won or more A
VM Study process (DCVM Job Plan) suitable for the characteristics of design changes was developed. As a result of testing the adequacy of
the DCVM Job Plan developed in this study, it was investigated that the DCVM Job Plan can be easily applied to the design change stage
by practitioners and can be used by the client as a reliable data in the process of reviewing the adequacy of the VM results. |