A Study on the Compression of Construction Time by Network Analysis System(PERT.CPM) |
Abstract |
A model network has been set up by adopting a simple network which can use a subnetwork for building construction.A time-cost algorithm has been designed for compressing the construction time to minimize the construction cost by relating the duration of construction activities to the construction cost.This a algorithm begins compressing the construction time starting with an activity with the low pitched cost curve then gradually extending to an activity with the high-pitched cost curve. |