Title TACT Scheduling & Monitoring of Apartment Finish Works based on the BDM Technique
Authors Kim, Seon-Gyoo ; Yoo, Jae-Woo ; Kim, Dong-Sub ; Park, Jong-il
DOI http://dx.doi.org/10.6106/KJCEM.2014.15.2.003
Page pp.3-11
ISSN 1229-7534
Keywords CPM ; TACT ; PDM ; BDM ; Apartment Finish Works
Abstract As the recent construction projects have been carried out as a mixed-use complex project that includes architecture, civil, mechanical, electrical, and landscape, as well as become bigger and high-rise with the increased repetitive works, the TACT technique has received more attention as an effective method for achieving a target completion date by securing the continuous works. Although the TACT technique can maintain a steady flow without the interruption of works in order to utilize the resources of the repetitive works, it can not be considered as the systematic scheduling technique because the schedule computations are not possible as well as a critical path can not be recognized. This paper proposes the applicabilities of scheduling and monitoring the TACT schedule by the BDM technique as comparing and analyzing the methodologies for apartment finish works by the Excel, the Primavera(P6) based on the PDM technique, and the Beeliner based on the BDM technique that is a new networking technique, respectively.